|
Power System Studies
This
webpage describes system analysis performed by NEPSI
in relation to the application of medium-voltage harmonic
filter banks and capacitor banks. It outlines
the typical analysis performed by NEPSI in evaluating
the possible system impacts related to the installation
and switching of medium-voltage harmonic filter banks
and shunt capacitor banks.
NEPSI's
engineering evaluation is centered on the design, specification,
and system impact of new and/or existing capacitor banks
and harmonic filter banks. NEPSI's recommendations will
typically be paid for by savings resulting from one
or more of the following:
-
Increased
savings from power factor penalties by optimizing
controls and bank size to utility rate structure.
-
Reduced
installation cost.
-
Reduced
capacitor bank and harmonic filter bank cost.
-
Elimination
or reduction of negative system impacts related
to capacitor bank installation.
The
engineering evaluation described herein, illustrate
the engineering capabilities of Northeast Power Systems,
Inc. All capacitor/filter bank evaluations will
vary in some degree, and is dependent upon system characteristics
and the type of equipment to be purchased or analyzed.
For a detailed quote for a power system evaluation,
contact NEPSI or one of NEPSI's sales representatives.
As with all power system evaluations, NEPSI will provide
a performance guarantee with a subsequent purchase of
either a harmonic filter or capacitor bank. This performance
guarantee is unmatched by any engineering consulting
firm or manufacturer.
Introduction
The installation of
a large shunt capacitor bank or harmonic filter bank
raises concerns primarily in the areas of harmonic distortion,
harmonic resonance, switching surges, and over voltage
as a result of the installation of power factor correction
equipment. It is prudent to perform a capacitor/harmonic
filter bank evaluation before equipment is purchased
so that any adverse conditions, added costs, and/or
cost reductions, can be accounted for and identified
in the design stages.
The
installation of a large shunt capacitor bank or harmonic
filter bank raises some or all of the concerns listed
in the Table 1 below. These concerns are evaluated
by on-site power system measurements and digital simulations
using sophisticated power system software. The
measurements provide the ambient distortion levels,
operating voltage, and other data required to validate
and perform digital simulations. The digital simulations
calculate system performance, and are used to predict
and mitigate power system problems before they occur,
so that special design requirements and cost can be
accounted for in the planning stages rather than in
the construction or commissioning phase.
|
Table 1 - Concerns Relating to the
Installation of Power
Factor Correction Equipment
|
|
|
|
|
|
|
|
|
|
The
scope of work required in an evaluation is divided
up as follows:
-
Power
system measurements and data collection
-
Short
circuit analysis
-
Load
flow analysis
-
Transient
Analysis
-
Filter/capacitor
bank design and specification
-
Development of installation specification
A
description of each of these analyses is provided
below.
Power
System Measurement &
Data Collection
The
primary purpose of measurement and data collection
is to collect the necessary data to perform the capacitor/filter
bank engineering evaluation. Data is collected
for normal and abnormal operating conditions, as well
as for future system conditions or enhancements.
It involves power system measurements, data validation,
and discussions with plant personnel. This task
may be performed by either NEPSI or plant personal
with direction from a NEPSI certified power engineer.
Data Collection and Validation
Data
required to perform a capacitor/filter bank engineering
evaluation is provided below.
-
Impedance
data, including one-line diagrams, location of existing
and future capacitor/filter banks, generators, motors,
and non-linear loads
-
Utility
system data.
-
Digital
copy of system data if available.
-
Equipment
ratings and relay settings where necessary to perform
the evaluation.
-
Normal
and abnormal system conditions and operating practices.
- Future
expansion and/or system changes.
The
validity of the system data is checked by a NEPSI power
engineer. Questionable data will be brought up
and checked on-site.
Power
System Measurements
Power
system measurements may be taken to quantify the existing
power factor, load level, operating voltage, harmonic
distortion levels and other power quality concerns.
In
some cases, capacitor banks and or loads may have to
be switched off to collect significant data, such as
background voltage distortion levels. If this
switching operation is necessary, a plan to do so will
be submitted in advance for consideration and approval.
Harmonic
Analysis
Harmonic
analysis involves the use of sophisticated computer
programs to identify and predict potential harmonic
problems and mitigation techniques. NEPSI’s harmonic
analysis program provides features that help in the
identification of harmonic problems. Significant
features include:
-
Harmonic
Impedance Scans.
-
Harmonic
Amplification Scans.
-
Voltage
and current distortion calculations.
-
Sensitivity
analysis
Harmonic
Impedance Scans
Impedance
scans are used to determine where resonant conditions
exist. They are basically an impedance verses
frequency plot of the system looking from the harmonic
current source. The Figure below shows two impedance
scans with harmonic resonance near the 4th, 7th, order
harmonics. The scan show the response of a system when
capacitors are installed on electrical system verses
a harmonic filter.
Impedance
scans are developed for both normal and abnormal operating
conditions as well as future expansions.
|
|
Figure
1 - Impedance
Scan
|
Current Amplification Scans
Current
amplification plots have the same general appearance
as impedance scans, but with a very different meaning.
These plots show the current magnification/attenuation
versus frequency at a given bus for a one-amp injection
at another bus in the system. These scans are
used for finding localized resonant problems.
They aid in the identification of negative interactions
that may exist between surrounding electrical equipment,
non-linear loads, and the planned and/or existing capacitor/filter
bank.
Voltage
& Current Distortion Calculations
In addition to the scans above, voltage distortion calculations
can be performed throughout the power system to confirm
that the system meets IEEE 519 requirements for voltage
and current distortion. Other local or international
standards or limits may be used at the request of the
customer. With a purchased study and harmonic
filter or capacitor bank, NEPSI will provide performance
guarantees against IEEE-519 limits. This performance
guarantee is unmatched by our competitors or consulting
engineering firms.
|
Maximum Harmonic
Current Distortion in % of IL
(Current Distortion Limits for
General Distribution Systems (120 volt
thru 69,000 Volts)
|
|
Individual Harmonic Order (Odd
Harmonic)
|
|
ISC/IL
|
<11
|
11<h<17
|
17<h<23
|
23<h<35
|
35<h
|
TDD
|
|
<20*
|
4.0
|
2.0
|
1.5
|
0.6
|
0.3
|
5.0
|
|
20<50
|
7.0
|
3.5
|
2.5
|
1.0
|
0.5
|
8.0
|
|
50<100
|
10.0
|
4.5
|
4.0
|
1.5
|
0.7
|
12.0
|
|
100<1000
|
12.0
|
5.5
|
5.0
|
2.0
|
1.0
|
15.0
|
|
>1000
|
15.0
|
7.0
|
6.0
|
2.5
|
1.4
|
20.0
|
|
Even harmonics are limited to
25% of the odd harmonic limits above.
|
|
Current distortion that results
in a direct current offset, e.g., half wave converters
are not allowed.
|
|
* All power generation equipment
is limited to these values of current distortion,
regardless of actual ISC/IL.
|
|
Where ISC = Maximum
short circuit current at point-of-common-coupling.
IL = Maximum demand load current
(fundamental frequency) at point of common coupling.
|
|
Voltage Distortion
Limits
|
|
Bus Voltage at PCC
|
Individual Voltage
Distortion (%)
|
Total Voltage Distortion
THD (%)
|
|
69 kV and below
|
3.0
|
5.0
|
|
69.001 kV thru 161 kV
|
1.5
|
2.5
|
|
161 kV and above
|
1.0
|
1.5
|
|
NOTE: High voltage systems can have up to
2.0% THD where the cause is an HVDC terminal that
will attenuate by the time it is tapped for a
user.
|
Sensitivity Analysis
Sensitivity
analysis is very important when doing harmonic analysis.
Variations in capacitor and reactor impedance’s, as
well as source impedance, can greatly affect voltage
and current distortion calculations. The sensitivity
analysis feature included in NEPSI’s harmonic analysis
software is utilized to determine if any adverse system
conditions exists due to slight variations in system
and/or equipment impedance’s. This feature is
especially useful in the design of harmonic filters
where the worse case harmonic duties must be calculated.
Short Circuit
Analysis
A
short circuit analysis is used to calculate system fault
current levels to determine the interrupting and withstand
adequacy of the power system equipment and associated
protective devices. It provides a guide in the
selection and rating or setting of protective devices
such as direct-acting trips, fuses, and relays and the
bases for the short circuit rating required for the
capacitor or harmonic filter bank.
The
short circuit analysis is typically limited to the major
buses (nodes) and equipment connected directly to the
capacitor or filter bank. It may be expanded to
include other busses at the customers request, in which
case a specific work scope would be developed.
The short circuit calculation will account for local
generation, utility impedance, and short circuit current
contributions from motors. The cases selected
for the short circuit calculation will depict the power
system configuration for which the three phase bolted
fault short circuit currents will be at a maximum.
All comparisons of interrupting device short circuit
ratings or capabilities will be based on this “worst
case” condition.
Load Flow
Analysis
A
load flow analysis is conducted to predict power flow
magnitudes, power factor, voltage levels and losses
in branches of the system based on the specified operating
conditions. The results are used to determine
one or more of the following:
-
Recommended
transformer tap settings to maintain proper voltage
level.
-
Size
of capacitor/filter banks to maintain an acceptable
power factor and/or voltage level.
-
Equipment
rating (Ampacity).
-
Contingency
Analysis
-
Losses
A
load flow study will investigate system steady state
load performance under normal and abnormal operating
conditions. All significant system loads (watt
and var components) and power sources (utility, co-gen,
etc.) relating to the filter/capacitor bank installation
are modeled. Where possible, system equivalents
may be developed. The modeling can be expanded to include
more of the system at the request of the customer, in
which case, a specific work scope will be developed.
Switching
Surge Analysis
Switching
surges occur during most switching operations.
They occur during the transition when the system is
changing from one steady state operating condition to
another (this occurs during energization and de-energization
of all equipment). The magnitude of the switching
transient depends upon switching time and the resistive,
capacitive, and inductive characteristics of the system.
Capacitor switching and miss-operation of switches due
to re-strike and pre-strike generally cause the more
severe switching surges.
The
Electromagnetic Transients Program (EMTP) is typically
used to investigate switching surges and can produce
actual waveforms as shown in in the figure below.
Transient simulation models require more detail than
60 Hz models used in load flow, short circuit, and harmonic
analysis programs. Due to this increase level
of detail, the circuit elements of concern are usually
modeled in detail, while the remainder of the system
is modeled as a lumped circuit parameter.
|
|
|
Figure
2
- Typical
Waveform Plot Produced
By EMTP
|
Where switching surges are found to be a potential problem,
recommendations on their mitigation will be included
in the final report.
Filter Bank/Capacitor
Bank Design
& Specification
The design and specification of the capacitor/filter
bank is based on the analyses provided above. The Capacitor/Filter
bank performance is evaluated as part of the load flow
and harmonic analyses while the short circuit requirements
are evaluated from the short circuit analysis. This
task involves the functional specification of the specific
components within the filter/capacitor bank to meet
the performance requirements imposed. A close interaction
with plant/utility engineers is required so the bank
can be designed with the desired operating controls
and protection system. A guide form specification and
functional specification is then provided so that the
customer can go out for competitive bid.
The
specification will typically contain the following:
-
Capacitor
ratings
-
Reactor
ratings
-
Filter
bank configuration
-
Protection
requirements
-
Switch
requirements
-
Disconnecting
requirements
-
Layout
requirements
-
Warranty
requirements
-
Transient
inrush reactor requirements
-
Control
requirements
-
Approved
supplier list
Northeast
Power Systems, Inc.
66 Carey Road
Queensbury, New York 12804
Phone: 518-792-4776
Fax: 518-792-5767
E-mail:
sales@nepsi.com
Website: www.nepsi.com
Copyright © 1999
- 2009 Northeast Power Systems, Inc.
|