|
Case
Study - Induction Furnace Application
Introduction
Indianapolis
Casting Company (ICC), a foundry located in Indianapolis, Indiana,
contacted Northeast Power Systems with the desire to obtain an 8064
kvar 13.8 kV single step capacitor bank. ICC was looking for a quick
delivery of three weeks due to power quality problems associated
with the startup of a multi-million dollar 10 MW induction furnace.
The induction furnace manufacturer and ICC speculated the power
quality problems were caused by waveform notching or harmonics created
by the new induction furnace’s power electronic circuitry.
The proposed capacitor bank was being installed to attenuate the
line notching and higher order harmonics.

Figure
1 -
Power Quality Problems Associated With Induction Furnaces Can Be
Corrected With Harmonic Filter Banks and Shunt Capacitor Banks
Due
to the economic need to get the furnace operational, the project
was highly visible and involved engineers from Northeast Power Systems,
Inc. (NEPSI), the electric utility, the induction furnace manufacturer,
ICC, and engineers hired by ICC to oversee the project.
ICC’s
Power System
ICC
is served from two separate Indianapolis Power and Light (IP&L)
132kV transmission lines as shown in Figure 2. The voltage of each
line is dropped to 13.8kV through two 24/32/40 MVA transformers
(named North and South Bus Transformers). The new Induction
furnace is connected to the North Bus through the North Bus Transformer).
The North Bus transformer has an impedance of 9.73%. The North
and South bus are tied together through a normally open tie.
The
new induction furnace is rated at 10.0MW and receives power from
the North Bus through a three winding 11.2 MVA transformer with
an impedance of 5.5%. In addition to the new induction furnace,
the North bus also feeds a large machine shop, other electric furnaces,
an IP&L distribution circuit, and the proposed 8064 kvar 13.8kV
single step fixed capacitor bank.
During
the commissioning period of the induction furnace, electrical problems
involving insulation failures and nuisance drive miss-operations
occurred in the machine shop. These problems were very costly
to ICC, which led to the eventual purchase of the 8050 kvar fixed
capacitor bank.

Figure
2 – ICC Power System
Showing Typical
Power Flow and System Voltages
Proposed
Capacitor Bank
The
proposed capacitor bank consists of twenty-one individually fused
600 kvar, 9.96kV double bushing capacitors connected in an ungrounded-wye
configuration. This equates to 8064 kvar at a system voltage
of 13.8kV. Due to space constraints and the requirement for a quick
and simple installation, a metal-enclosed bank was chosen (shown
if Figure 3). The capacitor bank is equipped with an integral
500 MVA 15kV ABB vacuum circuit breaker. This allowed for
direct connection to ICC’s 13.8kV North Bus. Over-current protection
is provided by an MDP over-current relay that has both phase and
ground fault relays. Blown fuse detection is provided by a
relay that will trip the bank off line if two or more capacitor
fuses operate.
Figure
3 –
Picture of 8050 kvar metal-enclosed capacitor bank (center).
To left is a 1500 kvar
metal-enclosed bank and to the right is a synchronizing switch enclosure
for the
8050 kvar Bank. All items above were manufactured by NEPSI.
Concerns
With Installation of Capacitor Bank
During
NEPSI’s capacitor bank design process, there were three primary
areas of concerns relating to the installation and energization
of the proposed capacitor bank. The primary areas of concern were
as follows:
1.
North Bus operating voltage range
2.
Harmonic distortion and resonance
3.
Reduction in notch depth and ringing attenuation
As
part of the design process, NEPSI’s power systems engineers performed
a power system evaluation to address the above concerns. A brief
description of the evaluation and the results are presented in the
remainder of this document.
Power
System Evaluation Results
Voltage
range concerns were analyzed with a load flow program, while the
notching/ringing problem and harmonic concerns were addressed with
a harmonic analysis program.
Load
Flow Calculations
Several
load flow calculations were made to determine the operating voltage
of the 13.8 kV North Bus at ICC for various operating conditions.
The calculations were also made to determine the optimal position
for the fixed tap, which exist on the North Bus 132 kV/13.8 kV transformer
bank. A summary of the results are provided in Table-1 below.
IP&L
indicated that their system was designed to operate in a range of
+/- 5% on the primary and/or secondary of the ICC North transformer.
The actual voltage as measured for the entire year of 1998 ranged
from 0.97 to 1.04 PU with a normal operating voltage range of 1.0
to 1.035 PU. The tap position was selected based on the normal operating
range of 1.0 to 1.035 PU.
The
loading used in the load flow calculations was based on load reports
that were provided by ICC for the first week of 1999. The loadings
were based on maximum and minimum load conditions. It was assumed
that the maximum load conditions were all coincident in time. The
minimum load condition was assumed as 0 MW and 0 MVARS. By selecting
these two load conditions, a conservative maximum and minimum voltage
in the system was calculated.
Cases-1
shows the operating voltage of the system for the existing system
conditions with the proposed capacitor bank on line at 8.064 MVARs.
As can be seen in Table 1, the voltage at the 13.8 kV North Bus
climbs to 1.089 PU or 15.02 kV. This voltage is above what would
be recommended for a safe operating voltage under ANSI standard
C84 for equipment rated with a nominal voltage of 13.8 kV. It would
result in pre-mature breakdown of insulation and possible failure
to sensitive electronic equipment, which is fed from the North Bus.
The other two cases under Case Name-1 shows the voltage to be within
the safe operating range for both ICC and IP&L.
Cases-2
shows the same cases as cases-1 but with the proposed capacitor
bank switched off. This condition would reflect what would exist
on the system with no capacitors. As can be seen in table 1, the
voltage still may climb to 1.062 PU giving the fact that the load
on the North bus is reduced to zero load. IP&L indicated that
the voltage for 1998 reached a maximum of 1.04 PU. The voltages
in our simulation did not exactly match because the loading at ICC
was assumed to be zero, but in fact had some magnitude, even during
low load periods, that would lead to some amount of voltage drop.
The results shown in Table 1 however, do indicate that the voltage
can climb to an un-acceptable voltage.
Cases-3
shows the operation of the system with the 8.064 MVAR capacitor
bank on-line with the taps moved up two positions to 135.3 kV. Under
this operating scenario, the operating voltage of 0.941 at full
load at the North Bus is to low for a nominal voltage delivered.
The maximum operation voltage, however, at the North bus reaches
a safe maximum of 1.043 PU.
Cases-4
simulations were made to determine if moving the taps only one position
would show a more favorable result. For a nominal operating voltage
on the utility, the voltage on the North bus is 0.968 PU under maximum
load conditions with the capacitor bank on. Under this scenario,
the voltage is slightly low. It should however be noted that IP&L
indicated that the normal voltage range is 1.0 PU to 1.035 PU. If
the average voltage in the system is 1.018 PU then this voltage
under maximum load conditions is tolerable at 0.988 PU.
|
Table
1 – ICC Load Flow Result
|
|
Case
Name
|
Utility
Voltage
|
ICC
Load
|
Capacitor
Status
|
Tap
Position
|
North
Bus Voltage
|
|
1A
|
1.035
|
Min
|
On
|
128.7kV
|
1.089
|
|
1B
|
1.0
|
Max
|
On
|
128.7kV
|
0.997
|
|
1C
|
0.97
|
Max
|
On
|
128.7kV
|
0.963
|
|
|
|
|
|
|
|
|
2A
|
1.035
|
Min
|
Off
|
128.7kV
|
1.062
|
|
2B
|
1.0
|
Max
|
Off
|
128.7kV
|
0.963
|
|
2C
|
0.97
|
Max
|
Off
|
128.7kV
|
0.930
|
|
|
|
|
|
|
|
|
3A
|
1.035
|
Min
|
On
|
135.3kV
|
1.043
|
|
3B
|
1.0
|
Max
|
On
|
135.3kV
|
0.941
|
|
3C
|
0.97
|
Max
|
On
|
135.3kV
|
0.908
|
|
|
|
|
|
|
|
|
4A
|
1.035
|
Min
|
On
|
132.0kV
|
1.069
|
|
4B
|
1.0
|
Max
|
On
|
132.0kV
|
0.968
|
|
4C
|
0.97
|
Max
|
On
|
132.0kV
|
0.935
|
Based
on the forging results, NEPSI recommended that IP&L move their
transformer tap on the North transformer from the existing tap of
128.7 kV to 132 KV. The maximum voltage may reach as high as 1.069
per unit when the capacitor banks are on and there is no load on
the North Bus. Based on this result NEPSI also recommended that
the capacitor bank be modified with a supervisory relay, which monitors
the bus voltage and opens the capacitor breaker if the system voltage
exceeds 1.05 PU.
Harmonic Analysis
A
harmonic analysis utilizing a harmonic analysis program was performed
on the ICC system to evaluate the likelihood of harmonic resonance
when the capacitor bank is energized. Impedance scans were developed
to show how the system impedance varies with frequency for different
system configurations. The system model included the new capacitor
bank, distribution capacitors, 132kV and 13.8kV system impedances,
and ICC motor loads and capacitors.
A
total of 8 different impedance scans representing different system
configurations were made, and are listed in Table 2. The impedance
scan for Case 2A, shown in figure 4, shows that when the 8064 kvar
capacitor bank is energized, a resonance near the 5th
(5.4th harmonic) exist. This resonance is of only
slight concern, since measurements indicate very low levels of 5th
harmonic current. If 5th harmonic currents become
high enough to cause significant amounts of voltage distortion,
it may be necessary to remove three capacitors from the new capacitor
bank (yielding 6910 kvar and moving the resonant point to the 5.9th
harmonic).
|
Table
2 – ICC Harmonic Analysis Cases and
Results Summary
|
|
Case
Name
|
North
Bus MVAR
|
Distribution
Capacitor Status
|
Motor
Capacitors
|
Resonant
Point(s)
|
|
1
|
0
|
YES
|
NO
|
7.4
|
|
2
|
8.064
|
YES
|
NO
|
4.7/12.7
|
|
2A
|
8.064
|
NO
|
NO
|
5.4
|
|
3
|
6.91
|
YES
|
NO
|
4.9/13
|
|
3A
|
6.91
|
NO
|
NO
|
5.9
|
|
4
|
8.064
|
YES
|
NO
|
4.9/13
|
|
5
|
FILTER
|
YES
|
YES
|
3.5/8.8
|
|
5A
|
FILTER
|
NO
|
NO
|
3.6
|

Figure
4 –
Capacitor Energized with IP&L Distribution
Circuit
Connected to the South Bus
Line
Notching and Ringing Analysis
The
presence of distinct line notching and ringing from the induction
furnace resulted in discussions on how to best filter the ringing
that is associated with it. The ringing, more than likely, results
in double zero voltage crossings, which cause sensitive electronic
equipment to miss-operate (i.e. UPS, AC & DC drives). This section
discusses the best method and the worst method in reducing the line
notch associated with the induction furnace. By reducing the line
notch depth, the likely hood of a zero voltage crossing is less
likely to occur.
The
oscillation within the ring, or “ringing”, is caused by the switching
action of the SCR cells. This phenomenon is difficult to predict
but is usually not a problem if there is significant damping (resistance)
in the system. The ringing is caused by the ac line inductance and
distributed capacitance, which being in parallel, will have a natural
frequency response when excited by a step change in voltage. This
ringing can, if not properly damped, add significantly (as much
as the notch depth) to the total notch depth.
The
prediction or calculation of the ringing is very difficult and requires
an electromagnetic transients program (EMTP). The notch depth
however, can easily be calculated (ignoring the ringing). By showing
a reduction in the line notch depth, a corresponding reduction in
the ringing will occur.
Figure
5 –
Impedance Scans for
Notch Ring Calculations
Case 2 – System with Capacitor Bank Energized
Case 5 – System with Filter Bank Energized
Case-1 Existing System Without Capacitor Bank or Harmonic Filter
Bank
The
notch in the voltage waveform results from two phases that are successively
shorted to each other as the current commutates from cell to cell
in the rectifier. This line notching occurs twelve times per cycle
for a twelve-pulse rectifier. Four of these notches are twice as
deep as the other eight. The deep notches occur when the phase-to-phase
short occurs across the same phase that is measured. The other eight
are due to the interaction of the phases as they commutate.
The
notch depth can be calculated analytically by using the voltage
divider principle, since the voltage notch is the result of a phase-to-phase
fault through the system impedance. By using the impedance model
as developed in the harmonic scans, the voltage notch depth can
be calculated. Figure 5 shows three harmonic impedance scans. The
scans show the impedance of the ICC system looking from the North
13.8 kV bus. The per unit impedance at the 70th harmonic
is recorded for each scan. This impedance will be used as the source
impedance for the voltage divider to determine the notch depth for
the various system configurations.
The
notch depth for the existing system is shown in the calculation
below. It was calculated by using the plot shown above and the impedance
of the furnace transformer.
Xs:
Source Impedance at 70th harmonic (From Plot):
1.082 Per Unit
Xt:
Furnace Isolation Transformer Impedance at 70th Harmonic:
70 x (10/11.2) x 0.055 = 3.44 Per Unit
Notch
Depth % :
The
same calculations can be made for the other two cases shown in the
plot above. The results of all three are shown in Table 3 below.
|
Table
3 – Notch Depth Calculation Results
|
|
Case
Name
|
Case
Description
|
Notch
Depth
|
|
Case
1
|
Existing
System, no capacitor bank
|
23.9%
|
|
Case
2
|
Existing
System with capacitor bank
|
0.52%
|
|
Case
5
|
Existing
System with 4.8th filter bank
|
19.6%
|
As
can be seen from the results above the capacitor bank by itself
is the most effective means of reducing the notch depth and the
ringing associated with the notch. The harmonic filter is not effective
because the filter becomes inductive beyond its tuning point.
Conclusions
and Recommendations
To
avoid excessive voltage during light loads, NEPSI recommended that
the utility move the transformer tap on the North transformer from
the existing tap of 128.7 kV to 132 KV. The maximum voltage may
reach as high as 1.069 per unit under this operating condition when
the capacitor bank is energized and there is no load on the North
Bus. Based on this result, NEPSI recommended that the capacitor
bank be modified with a supervisory relay which monitors the bus
voltage and opens the capacitor breaker if the voltage exceeds 1.05
PU.
The
energization of the proposed 8064 kvar capacitor bank will create
a resonance near the 5.4th harmonic that is of only slight
concern since there is only small amounts of 5th harmonic
current injected from ICC. If the injection currents come
of such magnitude to cause high voltage distortion, three capacitors
may be removed from the bank to shift the resonance point to near
the 5.9th harmonic.
Line
Notch analysis indicates the capacitor bank will reduce the line
notching from 23.9% (existing system with IPL distribution circuit
connected to the North Bus) to 0.52%. If the capacitor bank
is changed to a filter bank, the ability of the capacitor bank to
reduce line notching will be greatly diminished to 19.6%.
Based
on the forgoing, NEPSI recommended the capacitor bank be installed
and energized. NEPSI also recommended that both voltage and
harmonic measurements be taken during the initial startup to check
for adverse system conditions and to verify the results of this
report.
|
Northeast
Power Systems, Inc.
|
| 66
Carey Road Queensbury, New York12804 |
| Phone:
518-792-4776 |
| Fax:
518-792-5767 |
| E-mail:
sales@nepsi.com |
| Website:
www.nepsi.com |
|