|
SCADA
Controlled Multi-Step
Automatic Controlled Capacitor Banks & Filter Banks
Introduction
SCADA
(Supervisory Controlled and Data Acquisition) controlled multi-step
metal-enclosed automatic capacitor banks and harmonic filter banks
can provide many benefits that are not available in standard metal-enclosed
capacitor banks. A SCADA controlled automatic capacitor bank provides
local and remote control, failure prediction and detection, reduced
operating cost, and an ability to boost distribution and transmission
system performance with supervisory control. This Technical Note
provides information on the benefits of SCADA controlled multi-step
capacitor banks as well as a common SCADA control package provided
by Northeast Power Systems, Inc. (NEPSI).
Detailed
specifications on SCADA controlled multi-step metal-enclosed capacitor
banks and harmonic filter banks are available from NEPSI by email.
You may request a copy at: Sales@nepsi.com

Figure
1 –
SCADA Controlled Automatic Capacitor Banks Offer Many Benefits
Over
Conventional
Metal-Enclosed Capacitor Banks
Background
Conventional
multi-step automatic capacitor banks consist of 2 to 5 steps of
shunt capacitors with total bank kvar ratings to 10,000 kvar. The
capacitors steps are automatically energized and de-energized with
vacuum switches to regulate voltage, power factor, or VARs on distribution
substations ranging in voltages from 4.16kV to 34.5kV. The banks
are shipped fully assembled and ready for interconnection. All switching
devices (including air-disconnect switches), protection and control
features are neatly packaged into a single unit to allow for direct
connection to the main bus of a distribution substation. A concrete
pad, external current transformer signal, three power cables, and
a ground wire is all that is required to connect these banks to
your system.
A
SCADA controlled bank offers the same benefits as conventional metal
enclosed banks, but goes one step further and allows for connection
to a SCADA system. These SCADA controlled banks provide the following
key benefits:
SCADA CONTROL
Figure
1 shows a typical block diagram of a SCADA controlled metal-enclosed
automatic capacitor bank. Key elements shown in the diagram are
as follows:
SCADA Input/Output Requirements
Table
1 below shows the typical I/O requirements of the RTU. NEPSI can
install and pre-wire the RTU and communication devices at the factory
or can leave space in the automatic metal-enclosed control cabinet
for installation by the customer.
|
Table
1 - SCADA Controlled Capacitor Bank
I/O
Requirements
|
|
Name
|
Type
|
Functional
Description
|
|
Supervisory
Control Enabled
|
Indicator/output
|
Provides
indication if Automatic Capacitor Bank can be supervisory
controlled.
|
|
Supervisory
Control Disabled
|
Indicator/output
|
Provides
indication that supervisory controls are disabled. This mode
of operation can only be performed by throwing a switch on
the capacitor bank control panel and is primarily used for
testing.
|
|
Return
to Automatic Control
|
Control/Input
|
Returns
control back to the capacitor banks automatic power factor
correction control system.
|
|
Stage
1 On
|
Control/Input
|
Turns
Stage 1 on when supervisory control is enabled - Automatic
Power Factor Control System gets disabled.
|
|
Stage
1 Off
|
Control/Input
|
Turns
Stage 1 off when supervisory control is enabled - Automatic
Power Factor Control System gets disabled.
|
|
Stage
2 On
|
Control/Input
|
Turns
Stage 2 on when supervisory control is enabled - Automatic
Power Factor Control System gets disabled.
|
|
Stage
2 Off
|
Control/Input
|
Turns
Stage 2 off when supervisory control is enabled - Automatic
Power Factor Control System gets disabled
|
|
Stage
3 On
|
Control/Input
|
Turns
Stage 3 on when supervisory control is enabled - Automatic
Power Factor Control System gets disabled.
|
|
Stage
3 Off
|
Control/Input
|
Turns
Stage 3 off when supervisory control is enabled - Automatic
Power Factor Control System gets disabled
|
|
Stage
1 On
|
Indicator/Output
|
Indicates
if Stage 1 is on
|
|
Stage
1 Off
|
Indicator/Output
|
Indicates
if Stage 1 is off
|
|
Stage
2 On
|
Indicator/Output
|
Indicates
if Stage 2 is on
|
|
Stage
2 Off
|
Indicator/Output
|
Indicates
if Stage 2 is off
|
|
Stage
3 On
|
Indicator/Output
|
Indicates
if Stage 3 is on
|
|
Stage
3 Off
|
Indicator/Output
|
Indicates
if Stage 3 is off
(Repeat
above Stage indicators for each stage)
|
|
Data
Acquisition Parameters
|
Output
Via DNP/Modus Protocol to RTU
(Specify
communication requirement of RTU)
|
Three
Phase Voltage, Average Voltage, L-L Voltage, Phase Currents,
Voltage Unbalance, Current Unbalance, Line Frequency, Phase
KW, Total KW, Phase Kvar, Total Kvar, Phase KVA, Total KVA,
Phase Power Factor, KW Thermal Demand, KVAR Thermal Demand,
KVA Thermal Demand, Maximum KW Demand, Maximum Kvar Thermal
Demand, Maximum KVA Thermal Demand, Maximum Total kW,
Maximum Total Kvar, Maximum Total KVA, Minimum Average Current,
Total kVARh, Net kVARh, Total kVARh, Max Phase Voltage THD,
Maximum Phase Current THD
|
|
Neutral
Unbalance Alarm
|
Indicator/Output
|
Provides
warning against a blown capacitor fuse condition.
|
|
Neutral
Unbalance Trip
|
Indicator/Output
|
Provides
indication that bank tripped on a blown capacitor fuse condition
|
|
Over-Voltage
Alarm
|
Indicator/Output
|
Provides
indication of an over-voltage alarm
(Only
required when bank is equipped with an over-voltage relay)
|
|
Over-Voltage
Trip
|
Indicator/Output
|
Provides
indication that the capacitor bank tripped on Over-Voltage
(Only
required when bank is equipped with an over-voltage relay)
|
|
Over-current
Trip
|
Indicator/Output
|
Provides
indication that the capacitor bank tripped on over-current.
(Only
required when the bank is equipped with an over-current relay)
|
Conclusion
This
Technical Note presented the benefits of SCADA controlled automatic
capacitor banks. It also presented a SCADA control scheme and the
input and output requirements of the scheme. It is important
that the customer properly specifies the requirements of the SCADA
system and anticipates the I/O requirements of the RTU. It
is in the customer’s best interest to specify an RTU and communication
device that is compatible with the Master SCADA system. To
ensure a fully functional automatic capacitor bank SCADA control
system, the manufacturer should be requested to install and test
the SCADA control system with the desired RTU.
|
Northeast
Power Systems, Inc.
|
66
Carey Road
Queensbury, New York 12804
|
| Phone:
518-792-4776 |
| Fax:
518-792-5767 |
| E-mail:
sales@nepsi.com |
| Website:
www.nepsi.com |
|